FINAL REPORT

04.01.2019

SUMMARY

This report is composition of two semester investigation of the Agricultural Engineering Building’s mechanical system. The overall goal of this thesis project was to research, analyze the existing mechanical system, propose alternatives and determine if the alternative systems should be recommended for existing condition. 

The Agricultural Engineering Building is located in University Park, PA. Originally built in 1937, the Agricultural Engineering Building got a major renewal by keeping the building’s original facades and adding new spaces to the back with a modern feel. This 4 story building, including basement, is approximately 94,000 square feet and used mainly for the laboratory, classrooms and small portion of offices for the agricultural engineering department. The renewal cost for this building was $44 million, making the cost per square foot about $470.

Two alternatives are being proposed for this building, having central cooling and heating plant, instead of connect to campus chilled water and steam utility loop. The main study of the proposed design was to see if producing chilled and hot water on site would be cheaper than using campus utility loop. For central cooling plant, the air and water cooled chiller with cooling tower were studied and compared with energy usage and cost efficiency. Same process has been done for central heating system, the non-condensing and condensing boiler.

The breadth topics includes acoustic and daylighting. For acoustics breadth topic, the airborne and structure-borne sounds produced by air cooled chiller were studied and proposed with solutions to both problems. For daylighting topics, the research of the overhang type and study of utilizing overhangs on the south side of the building was done.

Executive Summary

NEWS FEED

Fall Semester

Aug.2018 - Dec.2018

 12.07     Proposal

 11.16     Draft Breadth Topics

 10.29     Tech Report 3

 10.26     Abstract Color and Content

 10.17     Building Statistics Part 2 - Posted on CPEP

 10.01     Building Statistics Part 1- Posted on CPEP

 09.28     Tech Report 2​

 09.14     Bio Sketch Peer Review & Correction

 09.12     Resume Posted

 09.12     Bio Sketch Posted

 09.10     CPEP Website - Full Menu Functional

 09.07     Tech Report 1

 09.04     CPEP Home Page Draft

 09.04     Mailed AE Dept. Thank You Letters to primary contacts

 08.31     Building Statistics Part 1 - Electronic Copy

 08.31     Career Fair Hosting/Event Assistance Sign up Complete

 08.27     Resume Submitted for AE Career Fair listing 

 08.27     Obtained Project Documentation

 08.27     Turned in Project Initiation Checklist Part 2

 08.20     Confirmed Master List Information

 08.20     Turned in Project Initiation Checklist Part 1

 08.13     Owners Permission Received

Spring Semester

Jan.2019 - May.2019

 00.00     Turned In with Studio Key

 00.00     Final Thesis Checklist Complete

 00.00     CPEP Site Ready for Final Review

 00.00     Thesis Research CPEP Page Completed

 00.00     ABET Assessment Chart & Reflection Completed

 04.09     Presentation / Thesis Defense Completed

 04.08     Final Presentation (PPT & PDF) Posted

 04.01     Final Report - Posted

​ 03.28     Progress Schedule Milestone 3 Accomplished 

 03.27     Presentation Outline - with Draft / Sample Slides

​ 03.14     Progress Schedule Milestone 2 Accomplished 

​ 02.14     Progress Schedule Milestone 1 Accomplished 

​ 01.17     Spring Planning / Project Schedule 1st Submission

 01.14     Approved / Updated Proposal

Final Reprt PDF